CEIP-1

Coastal Embankment Improvement Project

Project Overview


Works Package 01 (W-01)
  • Contractor
  • Contact Signed Date
  • Notice Commence
  • Contract Completion Date
  • Contract Value
  • Polders under W-01
  • CHWE China
  • November 1, 2015
  • January 26, 2016
  • June 30, 2023

  • 32, 33, 35/1, 35/3

  • # Indicator Name Unit Target by WP 01 Achieved by WP 01 % Completed
    1 Length of Upgraded Embankment Km 200.617 200.617 100%
    2 Drainage Structures Replaced No 38 38 100%
    3 Drainage Structures Repaired No 2 2 100%
    4 Flushing inlets Replaced No 29 29 100%
    5 Flushing inlets Repaired No 14 14 100%
    6 Length of Drainage Channels Upgraded Km 150.299 150.299 100%
    7 Length of River Bank Protection Km 4.250 4.250 100%
    8 Length of Slope Protection Km 19.766 19.766 100%

    Works Package 02 (W-02)
  • Contractor
  • Contact Signed Date
  • Notice Commence
  • Contract Completion Date
  • Contract Value
  • Polders under W-01
  • CICO (China)
  • March 8, 2017
  • July 12, 2017
  • September 30, 2023

  • 39/2C, 40/2, 41/1, 43/2C, 47/2, 48

  • # Indicator Name Unit Target by WP 02 Achieved by WP 02 % Completed
    1 Length of Upgraded Embankment Km 208.093 203.586 97.00%
    2 Drainage Structures Replaced No 51 51 100%
    3 Drainage Structures Repaired No 3.0 3.0 100%
    4 Flushing inlets Replaced No 51 51 100%
    5 Flushing inlets Repaired No 31 31 100%
    6 Length of Drainage Channels Upgraded Km 154.877 154.877 100%
    7 Length of River Bank Protection Km 5.579 5.579 100%
    8 Length of Slope Protection Km 9.365 9.365 100%

    Contact Us


    On project matters:

    Communication Officer, PMU, CEIP-1, Phone: +8802-222299373
    Email: pdpmuceip@gmail.com

    On website issues:
    Md Mahidur Rahman Khan
    Deputy Team Leader,
    Third Party M&E for Overall Project Implementation, Sheladia Associates, Inc. (USA),
    Phone: 02-4881-0167 (Secretary Ms. Moly),
    Email: dtl.me.ceip1@gmail.com

    Office Address


    Project Management Unit
    Coastal Embankment Improvement Project, (CEIP-1)
    72 Green Road (10th floor), Pani Bhaban
    Panthapath, Dhaka- 1215
    Phone: +8802-222299373


    google map embed iframe