Skip to content

Project Overview



Status of Goods Packages under CEIP-1
SL. No Package No Description of Goods Adver. of Bid Receipt of Bid Contract Signing Date Remarks
1. CEIP-1/G-1 Procurement of 10 Nos. 4-WD Motor Vehicle & 2 Nos. Microbus 25/12/14 25/01/15 18-11-2015 & 07-01-2016 Supply Completed
2. CEIP-1/G-2 Procurement of 10 Nos. 4-WD Motor Cycle (125 CC) with accessories and related Services 09/07/15 10/08/15 04-10-2015 Supply Completed
3. CEIP-1/G-3 Procurement of Speed Boat with engine and other accessories and related Services. - - - The procurement is planned to be taken up at the later stage of the project.
4. CEIP-1/G-4 Supply of Desktop Computer, Laptop, Printer, & UPS with accessories under CEIP-1 19/03/2014 09/04/2014 08-06-2014 Supply Completed
5. CEIP-1/G-5 Supplying Engineering Equipment: 1)Levelling instrument-5 Nos. & 2) Total Station -2 Nos. with accessories. 09/07/15 10/08/15 04-10-2015 Supply Completed
6. CEIP-1/G-6 Office Equipment: 1)Multimedia Projector, 2)Air cooler, 3)PABX Intercom System, 4)Photocopier, 5)Fax, 6)Scanner, 7)Plotter (36" Size) with accessories and related services under CEIP-1. 01/04/2014 12/05/2014 09-06-2014 Supply Completed
7. CEIP-1/G-7 Procurement ofOffice Furniture N/A 20/02/2014 24-02-2014 Supply Completed
8. CEIP-1/G-8 Procurement of Motor Vehicle: 4WD Vehicle-5 Nos. - - - This Package has been annualed in the REvised DPP (RDPP)
9. CEIP-1/G-9 Procurement of Motor Cycle-10 Nos. - - - This Package has been annualed in the REvised DPP (RDPP)
10. CEIP-1/G-10 Procurement of Speed Boat with engine & other accessories 4 Nos. - - - This Package has been annualed in the REvised DPP (RDPP)
11. CEIP-1/G-11 Procurement of Computers a) Laptop- 5 Nos & Desktop-5 Nos, b) Printer- 10 Nos. c) UPS- 5 Nos. and d) IPS- 5 Nos. 06/07/2017 25/07/2017 12-09-2017 Supply Completed
12. CEIP-1/G-12 Procurement of a) Levelling instrument-5 Nos. and b) Total Station- 2 Nos. - - - This Package has been annualed in the REvised DPP (RDPP)
13. CEIP-1/G-13 Procurement of a) Multimedia Projector- 2 Nos, b) Air cooler- 5 Nos, c) Photocopier- 5 Nos, d) Fax- 6 Nos, e) Scanner- 2 Nos, f) Spiral Binding Machine- 2 Nos. - - - This Package has been annualed in the REvised DPP (RDPP)
14. CEIP-1/G-14 Procurement of Motor Micro Bus- 1 No. - - - This Package has been annualed in the REvised DPP (RDPP)

Contact Us


On project matters:

Communication Officer, PMU, CEIP-1, Phone: +8802-222299373
Email: pdpmuceip@gmail.com

On website issues:
Md Mahidur Rahman Khan
Deputy Team Leader,
Third Party M&E for Overall Project Implementation, Sheladia Associates, Inc. (USA),
Phone: 02-4881-0167 (Secretary Ms. Moly),
Email: dtl.me.ceip1@gmail.com

Office Address


Project Management Unit
Coastal Embankment Improvement Project, (CEIP-1)
72 Green Road (10th floor), Pani Bhaban
Panthapath, Dhaka- 1215
Phone: +8802-222299373


google map embed iframe